[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895548":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},895548,581,1,"单选题","投标人针对工程量清单中工程量的遗漏或错误，可以采取的正确做法是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","即向招标人提出异议，要求招标人修改",false,{"key":16,"text":17,"correct":14},"B","不向招标人提出异议，风险自留",{"key":19,"text":20,"correct":21},"C","是否向招标人提出修改意见取决于投标策略",true,{"key":23,"text":24,"correct":14},"D","等中标后，要求招标人按实调整","投标人进行复核工程量的目的不是修改工程量清单对工程量清单。对工程量清单存在的错误，可以向招标人提出，由招标人统一修改，并把修改情况通知所有投标人；针对工程量清单中工程量的遗漏或错误，是否向招标人提出修改意见取决于投标策略：投标人可以运用一些报价的技巧提高报价的质量，争取在中标后能获得更大的收益。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]