[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895541":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},895541,581,1,"单选题","下列费用项目中，应由投标人确定额度，并计入其他项目清单与机架汇总表中的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","暂列金额",false,{"key":16,"text":17,"correct":14},"B","材料暂估价",{"key":19,"text":20,"correct":14},"C","专业工程暂估价",{"key":22,"text":23,"correct":24},"D","总承包服务费",true,"暂列金额应按照其他项目清单中列出的金额填写，不得变动材料暂估单价和专业工程暂估价均由招标人提供，为暂估价格，在工程实施过程中，对于不同类型的材料与专业工程采用不同的计价方法。招标人应预计总承包服务费用并按投标人的投标报价向投标人支付该项费用。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]