[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895534":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},895534,581,1,"单选题","关于工程量清单方式招标工程合同价格风险及风险分担，下列说法中正确的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","当出现的风险内容及幅度在招标文件规定的范围内时，综合单价不变",true,{"key":16,"text":17,"correct":18},"B","市场价格波动导致施工机具使用费发生变化时，承包人只承担5%以内的价格风险",false,{"key":20,"text":21,"correct":18},"C","人工费变化发生的风险全部由发包人承担",{"key":23,"text":24,"correct":18},"D","承包人管理费的风险一般由发承包双方共同承担","本题考查综合单价确定注意事项，B.市场价格波动导致施工机具使用费发生变化时，承包人只承担10%以内的价格风险;承包人承担5%以内的材料、工程设备价格风险，C:对于法律、法规、规章或有关政策出台导致工程税金、规费、人工费发生变化，并由省级、行业建设行政主管部门或其授权的工程造价管理机构根据上述变化发布的政策性调整，承包人不应承担此类风险，应按照有关调整规定执行。D 承包人管理费的风险一般由承包人全部承担。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]