[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895525":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},895525,581,1,"单选题","对于其他项目中的计日工，投标人正确的报价方式是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","按政策规定标准估算报价",false,{"key":16,"text":17,"correct":14},"B","按招标文件提供的金额报价",{"key":19,"text":20,"correct":21},"C","自主报价",true,{"key":23,"text":24,"correct":14},"D","待签证时报价","计日工应按照招标人提供的其他项目清单列出的项目和估算的数量，自主确定各项综合单价并计算费用。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]