[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895521":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},895521,581,1,"单选题","投标人在投标报价时，应优先被采用为综合单价编制依据的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","企业定额",true,{"key":16,"text":17,"correct":18},"B","地区定额",false,{"key":20,"text":21,"correct":18},"C","行业定额",{"key":23,"text":24,"correct":18},"D","国家定额","本题考查的是投标报价的编制方法和内容。综合单价计算基础主要包括消耗量指标和生产要素单价。应根据本企业的企业实际消耗量水平，并结合拟定的施工方案确定完成清单项目要消耗的各种人工、材料、机械台班的数量。计算时应采用企业定额，在没有企业定额或企业定额缺项时，可参照与本企业实际水平相近的国家、地区、行业定额，并通过调整来确定清单项目的人、材、机单位用量。各种人工、材料、机械台班的单价，则应根据询价的结果和市场行情综合确定。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]