[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895518":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},895518,581,1,"单选题","关于工程量清单方式招标工程合同价格风险及风险分担，下列说法中正确的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","当出现的风险内容及幅度在招标文件规定的范围内时，综合单价不变",true,{"key":16,"text":17,"correct":18},"B","市场价格波动导致施工机具使用费发生变化时，承包人只承担5%以内的价格风险",false,{"key":20,"text":21,"correct":18},"C","人工费变化发生的风险全部由发包人承担",{"key":23,"text":24,"correct":18},"D","承包人管理费的风险一般由发承包双方共同承担","招标文件中要求投标人承担的风险费用，投标人应考虑进入综合单价。在施工过程中，当出现的风险内容及其范围（幅度）在招标文件规定的范围（幅度）内时，综合单价不得变动，合同价款不作调整。对于主要由市场价格波动导致价格风险......根据工程特点和工期要求，一般采取的方式是承包人承担5%以内的材料、工程设备价格风险，10%以内的施工机具使用费风险。D是由承包人全部承担。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]