[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895514":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},895514,581,1,"单选题","招标控制价中暂列金额一般按分部分项工程费的一定比率参考计算，这一比率的范围是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","3%～5%",false,{"key":16,"text":17,"correct":14},"B","5%～10%",{"key":19,"text":20,"correct":21},"C","10%～15%",true,{"key":23,"text":24,"correct":14},"D","15%～20%","招标控制价编制时，暂列金额由招标人根据工程特点、工期长短，按有关计价规定进行估算，一般可以分部分项工程费的10%~15%为参考。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]