[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895511":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},895511,581,1,"单选题","关于标底与招标控制价的编制，下列说法中正确的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","招标人不得自行诀定是否编制标底",false,{"key":16,"text":17,"correct":18},"B","招标人不得规定最低投标限价",true,{"key":20,"text":21,"correct":14},"C","编制标底时必须同时设有最高投标限价",{"key":23,"text":24,"correct":14},"D","招标人不编制标底时应规定最低投标限价","《招标投标法实施条例》规定，招标人可以自行决定是否编制标底，一个招标项目只能有一个标底，标底必须保密。同时规定，招标人设有最高投标限价的，应当在招标文件中明确最高投标限价或者最高投标限价的计算方法，招标人不得规定最低投标限价。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]