[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895499":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},895499,581,1,"单选题","在编制脚手架工程量清单时，其工作内容不包括()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","场内、场外材料搬运",false,{"key":16,"text":17,"correct":14},"B","安全网的铺设",{"key":19,"text":20,"correct":14},"C","选择附墙点与主体连接",{"key":22,"text":23,"correct":24},"D","测试手动装置、安全锁等",true,"本题考查的是招标工程量清单的编制。计算脚手架工程量时，其工作内容包括：(1)场内、场外材料搬运；(2)搭、拆脚手架、斜道、上料平台；(3)安全网的铺设；(4)选择附墙点与主体连接；(5)测试电动装置、安全锁等；(6)拆除脚手架后材料的堆放。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]