[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895474":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},895474,581,1,"单选题","招标人对已发出的招标文件进行的必要修改，应当在投标截止时间（）天前发出。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","7",false,{"key":16,"text":17,"correct":14},"B","10",{"key":19,"text":20,"correct":14},"C","14",{"key":22,"text":23,"correct":24},"D","15",true,"本题考查的是招标文件的组成内容及其编制要求。招标人对已发出的招标文件进行必要的修改，应当在投标截止时间15 天前，招标人可以书面形式修改招标文件，并通知所有已购买招标文件的投标人。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]