[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895470":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},895470,581,1,"单选题","关于招标文件的澄清，下列说法中错误的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","投标人应以信函、电报等可以有形地表现所载内容的形式向招标人提出疑问",false,{"key":16,"text":17,"correct":18},"B","招标文件的澄清应发给所有投标人并指明澄清问题的来源",true,{"key":20,"text":21,"correct":14},"C","澄清发出的时间距投标截止日不足15天的应推迟投标截止时间",{"key":23,"text":24,"correct":14},"D","投标人收到澄清的确认时间可以是相对时间，也可以是绝对时间","招标文件的澄清将在规定的投标截止时间15天前以书面形式发给所有购买招标文件的投标人，但不指明澄清问题的来源。如果澄清发出的时间距投标截止时间不足15天，相应推迟投标截止时间。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]