[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895444":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},895444,581,1,"单选题","招标人和中标人在签订合同的谈判中， 为了防范货币贬值或者通货膨胀的风险， 一般通过( )约定风险承担方式",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","调整投标价格",false,{"key":16,"text":17,"correct":18},"B","价格调整条款",true,{"key":20,"text":21,"correct":14},"C","调整中标价格",{"key":23,"text":24,"correct":14},"D","调整工作范围","本题考查的是建设工程施工承包合同谈判的价格调整条款。对于工期较长的建设工程，容易遭受货币贬值或通货膨胀等因素的影响，可能给承包人造成较大损失，价格调整条款可以比较公正地解决这一承包人无法控制的风险损失。无论是单价合同还是总价合同，都可以确定价格调整条款，即是否调整以及如何调整等。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]