[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895440":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},895440,581,1,"单选题","在编制施工图预算的下列各项工作步骤中，同时适用于预算单价法和实物法的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","套人工、材料、机械台班定额消耗量",false,{"key":16,"text":17,"correct":14},"B","汇总各类人工、材料、机械台班消耗量",{"key":19,"text":20,"correct":14},"C","套当时当地人工、材料、机械台班单价",{"key":22,"text":23,"correct":24},"D","汇总人工、材料、机械台班总费用",true,"预算单价法与实物法首尾部分的步骤是相同的，都需要先进行编制前的准备工作，而最后都需要计算其他费用，汇总工程造价。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]