[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895432":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},895432,581,1,"单选题","编制某工程施工图预算，套用预算定额后得到的人工、甲材料、乙材料、机械台班的消耗量分别为15 工日、12m3.0.5m3.2 台班，预算单价与市场单价如下表所示。措施费为直接工程费的7%。则用实物法计算的该工程的直接费为（）元。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","4654.50",false,{"key":16,"text":17,"correct":14},"B","5045.05",{"key":19,"text":20,"correct":14},"C","5157.40",{"key":22,"text":23,"correct":24},"D","5547.95",true,"单位工程直接工程费=Σ（工程量×定额人工消耗量×市场工日单价）+Σ（工程量×定额材料消耗量×市场材料单价）+Σ（工程量×定额机械台班消耗量×市场直机械台班单价）=15×100+12×300+0.5×50+2×30=5185 直接费=5185×（1+7%）=5547.95",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]