[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895411":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},895411,581,1,"单选题","利用概算指标法编制拟建工程概算，已知概算指标中每100m2 建筑面积中分摊的人工消耗量为500 工日。拟建工程与概算指标相比，仅楼地面做法不同，概算指标为瓷砖地面，拟建工程为花岗岩地面。查预算定额得到铺瓷砖和花岗岩地面的人工消耗量分别为37 工日\u002F100m2 和24 工日\u002F100m2。拟建工程楼地面面积占建筑面积的65%。则对概算指标修正后的人工消耗量为（）工日\u002F100m2。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","316.55",false,{"key":16,"text":17,"correct":18},"B","491.55",true,{"key":20,"text":21,"correct":14},"C","508.45",{"key":23,"text":24,"correct":14},"D","845.00","修正结构件指标人工、材料、机械台班消耗量的计算公式如下： 结构变化修正概算指标的人工、材料、机械数量＝原概算指标的人工、材料、机械数量＋换入结构件工程量×相应定额人工、材料、机械消耗量－换出结构件工程量×相应定额人工、材料、机械消耗量即结构变化修正概算指标的人工消耗量：500＋24×65%－37×65%=491.55(工日\u002F100 平方米)。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]