[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895408":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},895408,581,1,"单选题","当初步设计深度不够，只有设备出厂而无详细规格、重量时，编制设备安装工程费概算可选用的方法是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","设备价值百分比法",true,{"key":16,"text":17,"correct":18},"B","设备系数法",false,{"key":20,"text":21,"correct":18},"C","综合吨位指标法",{"key":23,"text":24,"correct":18},"D","预算单价法","3)设备价值百分比法，又叫安装设备百分比法。当初步设计深度不够，只有设备出厂价而无详细规格、重量时，安装费可按占设备费的百分比计算。其百分比值（即安装费率）由相关管理部门制定或由设计单位根据已完类似工程确定。该法常用于价格波动不大的定型产品和通用设备产品，其计算公式为：设备安装费= 设备原价X安装费率（％)",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]