[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895403":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},895403,581,1,"单选题","某建设项目由各个单项工程构成，应包含在其中某单项工程综合概算中的费用项目是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工器具及生产家具购置费",true,{"key":16,"text":17,"correct":18},"B","办公和生活用品购置费",false,{"key":20,"text":21,"correct":18},"C","研究试验费",{"key":23,"text":24,"correct":18},"D","基本预备费","综合概算一般应包括建筑工程费用、安装工程费用、设备及工器具购置费。而B、C属于建设项目总概算中其他费用概算的内容，D属于建设项目总概算中预备费的内容。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]