[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895402":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},895402,581,1,"单选题","拟建工程初步设计与已完工程或在建工程的设计相类似而又没有可用的概算指标时采用，但必须对建筑结构差异和价差进行调整，适用于()方法。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","概算指标法",false,{"key":16,"text":17,"correct":18},"B","类似工程预算法",true,{"key":20,"text":21,"correct":14},"C","分组计算审查法",{"key":23,"text":24,"correct":14},"D","标准预算审查法","类似工程预算法在拟建工程初步设计与已完工程或在建工程的设计相类似而又没有可用的概算指标时采用，但必须对建筑结构差异和价差进行调整。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]