[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895400":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},895400,581,1,"单选题","已知某引进设备吨重为50t，设备原价3000万元，每吨设备安装费指标为8万元，同类国产设备的安装费率为15%，则该设备安装费为()万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","400",true,{"key":16,"text":17,"correct":18},"B","425",false,{"key":20,"text":21,"correct":18},"C","450",{"key":23,"text":24,"correct":18},"D","500","综合吨位指标法。当初步设计提供的设备清单有规格和设备重量时，可采用综合吨位指标编制概算，其综合吨位指标由相关主管部门或由设计单位根据已完类似工程的资料确定。该法常用于设备价格波动较大的非标准设备和引进设备的安装工程概算，其计算 (3.2.8) 公:式为设备安装费= 设备吨重X每吨设备安装费指标（元\u002F吨）",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]