[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895397":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},895397,581,1,"单选题","利用概算指标法编制拟建工程概算，已知概算指标中每100㎡建筑面积中分摊的人工消耗量为500工日。拟建工程与概算指标相比，仅楼地面做法不同，概算指标为瓷砖地面，拟建工程为花岗岩地面。查预算定额得到铺瓷砖和花岗岩地面的人工消耗量分别为37工日\u002F100㎡和24工日\u002F100㎡。拟建工程楼地面面积占建筑面积的65%。则对概算指标修正后的人工消耗量为()工日\u002F100㎡。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","316.55",false,{"key":16,"text":17,"correct":18},"B","491.55",true,{"key":20,"text":21,"correct":14},"C","508.45",{"key":23,"text":24,"correct":14},"D","845.00","结构变化修正概算指标的人工量=原概算指标的人工量+换入结构件工程量×相应定额 人工消耗量-换出结构件工程量×相应定额人工消耗量 拟建工程100㎡中楼地面面积=100×65%=65(㎡) 修正后100㎡的人工消耗量=500+24×65\u002F100-37×65\u002F100=491.55（工日）",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]