[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895396":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},895396,581,1,"单选题","关于设计概算的调整，下列说法正确的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","若设计概算已通过批准，则不得调整",false,{"key":16,"text":17,"correct":14},"B","一个工程可多次调整设计概算",{"key":19,"text":20,"correct":21},"C","当发生超出原设计范围的重大变更时，允许调整概算",true,{"key":23,"text":24,"correct":14},"D","当市场价格波动较大超出价差预备费时，允许调整概算","设计概算经批准后，一般不得调整。一个工程只允许调整一次概算。允许调整概算的原因包括以下几点：超出原设计范围的重大变更；超出基本预备费规定范围不可抗拒的重大自然灾害引起的工程变动和费用增加；超出工程造价调整预备费的国家重大政策性的调整。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]