[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895391":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},895391,581,1,"单选题","设计概算的三级概算是指()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","建筑工程概算、安装工程概算、设备及工器具购置费概算",false,{"key":16,"text":17,"correct":14},"B","建设投资概算、建设期利息概算、铺底流动资金概算",{"key":19,"text":20,"correct":14},"C","主要工程项目概算、辅助和服务性工程项目概算、室内外工程项目概算",{"key":22,"text":23,"correct":24},"D","单位工程概算、单项工程综合概算、建设项目总概算",true,"建设项目设计概算是以初步设计文件为依据，按照规定的程序、方法和依据，对建设项目总投资及构成进行的概略计算。设计概算文件的编制应采用单位工程概算、单项工程综合概算、建设项目总概算三级概算编制形式。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]