[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895385":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},895385,581,1,"单选题","常用于设备价格波动较大的非标准设备和引进设备的安装工程概算编制方法是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","预算单价法",false,{"key":16,"text":17,"correct":14},"B","扩大单价法",{"key":19,"text":20,"correct":14},"C","设备价值百分比法",{"key":22,"text":23,"correct":24},"D","综合吨位指标法",true,"各种安装工程概算编制方法的适用对象是一个常考的问题，尤其是设备价值百分比法和综合吨位指标法的区别。设备价值百分比法常用于价格波动不大的定型产品和通用设备产品；综合吨位指标法常用于设备价格波动较大的非标准设备和引进设备的安装工程概算。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]