[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895376":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},895376,581,1,"单选题","在工业项目的工艺设计过程中，影响工程造价的主要因素包括()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","生产方法、工艺流程、功能分区",false,{"key":16,"text":17,"correct":18},"B","建设规模、标准和产品方案",true,{"key":20,"text":21,"correct":14},"C","工艺流程、功能分区、运输方式",{"key":23,"text":24,"correct":14},"D","工艺流程、原材料供应、运输方式","工艺设计阶段影响工程造价的主要因素包括：建设规模、标准和产品方案；工艺流程和主要设备的选型；主要原材料、燃料供应情况；生产组织及生产过程中的劳动定员情况；“三废”治理及环保措施等。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]