[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895367":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},895367,581,1,"单选题","世界银行贷款项目的投资估算常采用朗格系数法推算建设项目的静态投资，该方法的计算基数是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","主体工程费",false,{"key":16,"text":17,"correct":18},"B","设备购置费",true,{"key":20,"text":21,"correct":14},"C","其他工程费",{"key":23,"text":24,"correct":14},"D","安装工程费","本题考查的是投资估算的编制。朗格系数法是以设备费购置费为基数，乘以适当系数来推算项目的静态投资。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]