[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895357":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},895357,581,1,"单选题","应满足的要求:满足生产使用功能要求;适应已选定的场址（线路走向）；符合工程标准规范要求;经济合理。投资估算分析不包括（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","过程投资总额分析",true,{"key":16,"text":17,"correct":18},"B","工程投资比例分析",false,{"key":20,"text":21,"correct":18},"C","分析设备及工器具购置费占建设总投资的比例",{"key":23,"text":24,"correct":18},"D","分析影响投资的主要因素","投资估算分析应包括以下内容：1)工程投资比例分析；2)分析设备及工器具购置费、建筑工程费、安装工程费、预备费、建设期利息占建设总投资的比例等；3)分析影响投资的主要因素；4)分析说明投资高低的原因。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]