[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895353":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},895353,581,1,"单选题","某建设项目投产后,应付账款的最低周转天数为15 天，预计年销售收入为12000 万元，年经营成本9000 万元,其中外购原材料、燃料7200 万元。则该项目的应付账款估算额为（）万元。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","500",false,{"key":16,"text":17,"correct":14},"B","375",{"key":19,"text":20,"correct":21},"C","300",true,{"key":23,"text":24,"correct":14},"D","125","应付账款周转次数=360／应付账款最低周转天数=360／15=24；应付账款=外购原材料、燃料动力费及其他材料年费用／应付账款周转次数=7200／24=300（万元）。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]