[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895344":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},895344,581,1,"单选题","在国外项目投资估算中，有初步的工艺流程图、主要生产设备的生产能力及项目建设的地理位置等条件，可套用相近规模厂的单位生产能力建设费用来估算拟建项目所需的投资额。以上投资估算方法适用于( )阶段。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目的投资设想",false,{"key":16,"text":17,"correct":18},"B","项目的投资机会研究",true,{"key":20,"text":21,"correct":14},"C","项目的初步可行性研究",{"key":23,"text":24,"correct":14},"D","项目的详细可行性研究","本题考查的是投资估算的概念及其编制内容。投资机会研究阶段的投资估算。此时应有初步的工艺流程图、主要生产设备的生产能力及项目建设的地理位置等条件，故可套用相近规模厂的单位生产能力建设费用来估算拟建项目所需的投资额，据此初步判断项目是否可行。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]