[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895299":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},895299,581,1,"单选题","某工程在建设期初预计和建设期第一年末实际发生的设备、工器具购置情况如下表所示。与建设期初相比，第一年末的设备、工器具价格指数为()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","98.02",false,{"key":16,"text":17,"correct":18},"B","108.11",true,{"key":20,"text":21,"correct":14},"C","110.72",{"key":23,"text":24,"correct":14},"D","119.70","设备、工器具价格指数=Σ（报告期设备工器具单价×报告期购置数量^）\u002FΣ（基期设备工器具单价×报告期购置数量）=（5×110+8×78+12×48+65×10）\u002F（100×5+75×8+50×12+8×65）×100%≈108.11%",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]