[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895285":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},895285,581,1,"单选题","某建设项目报告期建筑安装工程费为900万元，造价指数为106%，报告期设备、工器具单价60万元，基期单价为50万元，报告期购置数量10台，基期购置数量12台，报告期工程建设其他费为200万元，工程建设其他指数为103%，则该建设项目工程造价指数为()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","115.74%",false,{"key":16,"text":17,"correct":18},"B","110.16%",true,{"key":20,"text":21,"correct":14},"C","116.16%",{"key":23,"text":24,"correct":14},"D","113.65%","设备、工器具价格指数=Σ（报告期设备工器具单价×报告期购置数量）\u002FΣ（基期设备工器具单价×报告期购置数量）=（10×60）\u002F（10×50）=120% 建筑安装工程造价指数=（900+600+200）\u002F[（900\u002F106%）+（600\u002F120%）+（200\u002F103%）]=110.16%",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]