[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895254":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},895254,581,1,"单选题","下列用工项目中，属于预算定额与劳动定额人工幅度差的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工机械辅助用工",false,{"key":16,"text":17,"correct":14},"B","超过预算定额取定运距增加的运输用工",{"key":19,"text":20,"correct":21},"C","班组操作地点转移用工",true,{"key":23,"text":24,"correct":14},"D","机械维修引起的操作人员停工","人工幅度差主要是指在劳动定额中未包括而在正常施工情况下不可避免但又很难准确计量的用工和各种工时损失。主要包括：(1)各工种间的工序搭接及交叉作业相互配合或影响所发生的停歇用工；(2)施工 过程中，移动临时水电线路而造成的影响工人操作的时间(3)质量检查和隐蔽工程验收工作的影响；(4)班组操作地点转移用工；(5)工序交接时对前一工序不可避免的休整用工；(6).施工中不可避免的其他零星用工。选项A属于辅助用工的内容，选项B属于超运距用工，选项D属于机械台班幅度差的内容。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]