[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895244":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},895244,581,1,"单选题","砌筑10m3砖墙需基本用工20个工日，辅助用工为5个工日，超运距用工需2个工日，人工幅度差系数为10%，则预算定额人工工日消耗量为()工日\u002F10m3。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","27.7",false,{"key":16,"text":17,"correct":14},"B","29.0",{"key":19,"text":20,"correct":14},"C","29.2",{"key":22,"text":23,"correct":24},"D","29.7",true,"人工工日消耗量=（基本用工+辅助用工+超运距用工）×（1+人工幅度差系数）=(20+5+2)×(1+10%)=29.7（工日\u002F10m3）",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]