[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895213":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},895213,581,1,"单选题","根据施工过程工时研究结果，与工人所担负的工作量大小无关的必须消耗时间是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","基本工作时间",false,{"key":16,"text":17,"correct":14},"B","辅助工作时间",{"key":19,"text":20,"correct":21},"C","准备与结束工作时间",true,{"key":23,"text":24,"correct":14},"D","多余工作时间","本题考查的是施工过程分解及工时研究。准备和结束工作时间的长短与所担负的工作量大小无关，但往往和工作内容有关。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]