[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895210":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},895210,581,1,"单选题","下列工人工作时间消耗中，属于有效工作时间的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","因混凝土养护引起的停工时间",false,{"key":16,"text":17,"correct":14},"B","偶然停工（停水、停电）增加的时间",{"key":19,"text":20,"correct":14},"C","产品质量不合格返工的工作时间",{"key":22,"text":23,"correct":24},"D","准备施工工具花费的时间",true,"工人工作时间包括必须消耗时间和损失时间。必须消耗时间包括有效工作时间、休息时间和不可避免中断时间。有效工作时间是从生产效果来看与产品生产直接有关的时间消耗。包括基本工作时间、辅助工作时间、准备与结束工作时间的消耗。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]