[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895204":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},895204,581,1,"单选题","在工人工作时间分类中，由于材料供应不及时引起工作班内的工时损失应列入（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工本身造成的停工时间",true,{"key":16,"text":17,"correct":18},"B","非施工本身造成的停工时间",false,{"key":20,"text":21,"correct":18},"C","准备与结束工作时间",{"key":23,"text":24,"correct":18},"D","不可避免的中断时间","该题考核工人工作时间中施工本身造成的停工时间的内容。停工时间按其性质可分为施工本身造成 的停工时间和非施工本身造成的停工时间两种。施工本身造成的停工时间，是由于施工组织不善、材料供应不及时、工作面准本工作做得不好、工作地点组织不良等情况引起的停工时间。非施工本身造成的停工时间，是由于水源、电源中断引起的停工时间。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]