[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895201":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},895201,581,1,"单选题","通过计时观察资料得知：人工挖二类土1m3 的基本工作时间为6h，辅助工作时间占工序作业时间的2%。准备与结束工作时间、不可避免的中断时间、休息时间分别占工作日的3%、2%、18%。则该人工挖二类土的时间定额是（）工日／m3。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0.7",false,{"key":16,"text":17,"correct":18},"B","0.994",true,{"key":20,"text":21,"correct":14},"C","1.006",{"key":23,"text":24,"correct":14},"D","1.307","基本作业时间=6（h／m3）=0.75（工日／m3） 工序作业时间=0.75／（1－2%）=0.765（工日／m3） 时间定额=0.765／（1－3%－2%－18%）=0.994（工日／m3）",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]