[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895199":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},895199,581,1,"单选题","已知某挖土机挖土的一次正常循环工作时间是2min，每循环工作一次挖土0.5m3，工作班的延续时间为8h，机械正常利用系数为0.8，则其产量定额为( )m3\u002F台班。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","96",true,{"key":16,"text":17,"correct":18},"B","120",false,{"key":20,"text":21,"correct":18},"C","150",{"key":23,"text":24,"correct":18},"D","300","本题考查的是确定机械台班定额消耗量的基本方法。本题正确答案为A。 对于循环机械台班定额消耗量的确定的程序如下：(1)确定正常施工条件下1h循环次数和纯工作生产率。本题中1h循环次数为：60\u002F2=30; 1h纯工作生产率：30×0.5=15(m3\u002Fh)。 (2)确定机械一个台班的纯工作时间。本题中一个台班的纯工作时间为：8×0.8=6.4 (h)。 (3)确定机械的产量定额。本题中机械的产量定额=15×6.4 =96 (m3)。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]