[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895198":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},895198,581,1,"单选题","据计时观测资料得知：每平方米标准砖墙勾缝时间为10min，辅助工作时间占工序作业时间的比例为5%，准备结束时间、不可避免中断时间、休息时间占工作班时间的比例分别为3%、2%、15%。则每立方米砌体标准砖厚砖墙勾缝的产量定额为( )m3／工日。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","8. 621",false,{"key":16,"text":17,"correct":18},"B","8.772",true,{"key":20,"text":21,"correct":14},"C","9. 174",{"key":23,"text":24,"correct":14},"D","14. 493","本题考查的是确定人工定额消耗量的基本方法。1砖厚的砖墙，其每立方米砌体墙面面积的换算系数为1\u002F0. 24 =4. 17m2，则每平方米砌体所需的勾缝时间是：4.17×10 =41. 7min,每立方米砌体1标准砖厚砖墙勾缝的工序作业时间=41.7／(1-5%)=43. 895min;每立方米砌体1标准砖厚砖墙勾缝的定额时间= 43. 895\u002F（1-3% -2% -15%）=54. 869min=0.114工日。 每立方米砌体1标准砖厚砖墙勾缝的产量定额= 1\u002F0. 114=8.772 m3\u002F1日。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]