[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895191":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},895191,581,1,"单选题","在各种计时观察法中，精确度最高的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","选择法测时",false,{"key":16,"text":17,"correct":18},"B","接续法测时",true,{"key":20,"text":21,"correct":14},"C","写实记录法",{"key":23,"text":24,"correct":14},"D","工作日写实法","主计时观察法主要有三种，即测时法、写实记录法和工作日写实法，测时法的精确性较高。测时法分为选择测试法和接续测时法。采用选择法测时，当被观察的某一循环工作的组成部分开始，观察者立即开动秒表，当该组成部分终止，则立即停止秒表。然后把秒表上指示的延续时间记录到选择法测时记录（循环整理）表上，并把秒针拨回到零点。下一组成部分开始，再开动秒表，如此依次观察，并依次记录下延续时间。接续法测时也称作连续法测时，它是连续测定一个施工过程各工序或操作的延续时间。接续法测时每次要记录各工序或操作的终止时间，并计算出本工序的延续时间。它比选择法测时准确、完善，但观察技术也较之复杂。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]