[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895190":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},895190,581,1,"单选题","测编定额时，需对施工过程进行分解。对比工作过程的特点，工序还应具有的特征是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","人员编制不变",false,{"key":16,"text":17,"correct":18},"B","劳动工具不变",true,{"key":20,"text":21,"correct":14},"C","工作地点不变",{"key":23,"text":24,"correct":14},"D","工作时段不变","工序是工艺方面最简单的施工过程，表现为工作者、劳动对象、劳动工具和工作地点均不变，是编制施工定额时主要的研究对象；工作过程由同一工人或同一小组所完成的在技术操作上相互有机联系的工序的总合体，特点是人员编制不变，工作地点不变，而材料和工具可以变换，因此，本题选项B属于工序特征而不属于工作过程，B正确。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]