[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895163":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},895163,581,1,"单选题","单位工程投资估算指标的内容应该是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建筑安装工程费用",true,{"key":16,"text":17,"correct":18},"B","设备购置费用",false,{"key":20,"text":21,"correct":18},"C","设备、工器具购置费用",{"key":23,"text":24,"correct":18},"D","建筑安装工程费用与设备、工器具购置费用之和","建设项目综合指标指按规定应列入建设项目总投资的从立项筹建开始至竣工验收交付使用的全部投资额，^包括单项工程投资、工程建设其他费用和预备费等；单项工程指标指按规定应 列入能独立发挥生产能力或使用效益的单项工程内的全部投资额，包括建筑工程费、安装工程费、设 备、工器具及生产家具购置费和可能包含的其他费用。单位工程指标按规定应列入能独立没计、施工的工程项目的费用，即建筑安装工程费用。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]