[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895159":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},895159,581,1,"单选题","某挖土机挖土一次正常循环工作时间为50s，每次循环平均挖土量为0.5m3，机械正常利用系数为0.8，机械幅度差系数为25%，按8小时工作制考虑，挖土方预算定额的机械台班消耗量为( )台班\u002F1000m3。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","5.43",true,{"key":16,"text":17,"correct":18},"B","7.2",false,{"key":20,"text":21,"correct":18},"C","8",{"key":23,"text":24,"correct":18},"D","8.68","施工机械台班产量定额=(3600\u002F50)×0.5×8×0.8=230.4（m3／台班）；施工机械台班时间定额=1\u002F230. 4=0.00434（台班\u002Fm3）；预算定额机械台班消耗量=0.00434×(1+25%)×1000=5.43（台班\u002F1000m3）",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]