[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895153":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},895153,581,1,"单选题","在预算定额人工工日消耗量计算时，已知完成单位合格产品的基本用工为22 工日，超运距用工为4 工日，辅助用工为2 工日，人工幅度差系数为12%，则预算定额中的人工工日消耗量为（）工日。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","3.36",false,{"key":16,"text":17,"correct":14},"B","25.36",{"key":19,"text":20,"correct":14},"C","28",{"key":22,"text":23,"correct":24},"D","31.36",true,"本题考核预算定额中人工工日消耗量的计算方法。预算定额中人工工日消耗量包括基本用工、其他用工两部分。其他用工由超运距用工、辅助用工和人工幅度差组成。 人工幅度差=(基本用工+辅助用工+超运距用工）×人工幅度差系数=(22+4+2)×l2%=3.36(工日） 人工工日消耗量=22+4+2+3.36=31.36(工日）",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]