[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895151":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},895151,581,1,"单选题","关于预算定额人工、材料、机械台班消耗量的计算和确认，下列说法中正确的是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","人工消耗中包含超出预算定额取定运距后的超运距用工",false,{"key":16,"text":17,"correct":14},"B","材料损耗量按照材料消耗量的一定比例计算",{"key":19,"text":20,"correct":21},"C","各种胶结、涂料等材料的配合比用料，按换算法计算",true,{"key":23,"text":24,"correct":14},"D","按小组产量计算机械台班产量时，机械幅度差系数取10%","换算法是指各种胶结、涂料等材料的配合比用料，可以根据要求条件换算，得出材料用量。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]