[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895148":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},895148,581,1,"单选题","在计算预算定额人工工日消耗量时，基本用工中除包括完成定额计量单位的主要用工外，还应包括（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","劳动定额规定应增（减）计算的用工",true,{"key":16,"text":17,"correct":18},"B","劳动定额内不包括的材料加工用工",false,{"key":20,"text":21,"correct":18},"C","施工中不可避免的其他零星用工",{"key":23,"text":24,"correct":18},"D","质量检查和隐蔽","基本用工中包括完成定额计量单位的主要用工和劳动定额规定应增（减）计算的用工。B 属于辅助用工，C、D 属于人工幅度差。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]