[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895147":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},895147,581,1,"单选题","下列用工项目中，属于预算定额与劳动定额人工幅度差的是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工机械辅助用工",false,{"key":16,"text":17,"correct":14},"B","超过预算定额取定运距增加的运输用工",{"key":19,"text":20,"correct":21},"C","班组操作地点转移用工",true,{"key":23,"text":24,"correct":14},"D","机械维修引起的操作人员停工","预算定额中的人工幅度差包括工序搭接及交叉作业影响的停工、施工机械和临时水电路转移造成的停工、质量和隐蔽工程检查的影响、班组操作地点转移用工、对前一工序修复用工和其他零星用工。注意选项B不属于超运距用工，可另行计算二次搬运费。选项D 为干扰项，既不属于人工幅度差也不属于机械幅度差。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]