[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895138":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},895138,581,1,"单选题","概算指标与概算定额的区别在于（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","概算指标是与设计阶段相适应的计价依据",false,{"key":16,"text":17,"correct":18},"B","概算指标通常是以单位工程为对象",true,{"key":20,"text":21,"correct":14},"C","概算指标的编制应遵循平均水平的原则",{"key":23,"text":24,"correct":14},"D","概算定额中含有消耗量指标","在于项自划分和综合扩大程度上的差异，概算定额以单位扩大分项工程或扩大结构构件为对象编制，预算定额以单位分项工程或结构构件为对象编制",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]