[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895133":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},895133,581,1,"单选题","投资估算指标的编制步骤不包括（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","对比分析阶段",true,{"key":16,"text":17,"correct":18},"B","收集整理资料阶段",false,{"key":20,"text":21,"correct":18},"C","平衡调整阶段",{"key":23,"text":24,"correct":18},"D","测算审查阶段","投资估算指标的编制步骤包括收集整理资料阶段、平衡调整阶段、测算审查阶段。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]