[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895127":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},895127,581,1,"单选题","分部分项工程量清单项目的工程量应以实体工程量为准,对于施工中的各种损耗和需要增加的工程量，投标人投标报价时，应在（）中考虑。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","措施项目",false,{"key":16,"text":17,"correct":18},"B","该清单项目的单价",true,{"key":20,"text":21,"correct":14},"C","其他项目清单",{"key":23,"text":24,"correct":14},"D","预留金","本题考核分部分项工程量清单工程数量的计算。分部分项工程量清单项目的工程量应以实体工程量为准，并以完成后的净值计算;投标人投标报价时，应在单价中考虑施工中各种损耗和需要增加的工程量。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]