[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895126":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},895126,581,1,"单选题","工程量清单计价模式下，在招投标阶段对尚未确定的某分部分项工程费，应列入（）中。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","暂列金额",true,{"key":16,"text":17,"correct":18},"B","基本预备费",false,{"key":20,"text":21,"correct":18},"C","暂估价",{"key":23,"text":24,"correct":18},"D","工程建设其他费","暂列金额是指招标人在工程量清单中暂定并包括在合同价款中的一笔款项。用于施工合同签订时尚 未确定或者不可预见的所需材料、设备、服务的采购，施工中可能发生的工程变更、合同约定调整因素出现时的工程价款调整以及发生的索赔、现场签证确认等的费用。 暂估价是指招标人在工程量清单中提供的用于支付必然发生但暂时不能确定价格的材料的单价以及专业工程的金额。将两者概念相比较，可以发现暂列金额选项更加符合题意。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]